1999 MTIA Results - North, South
and West corridors
Alternative 3 Light Rail Transit
Alternative 3 follows:
- 14th Street
- Natural Bridge Road
- Riverview Blvd
- Norfolk Southern Railroad
- West Florissant Ave.
Planners designated the following stations
for this alternative:
- 14th Street
- N. Florissant at St. Louis Ave.
- Parnell at Natural Bridge Rd.
- Grand at Natural Bridge Rd.
- Fair Avenue at Natural Bridge Road
- Newstead at Natural Bridge Road
- Kingshighway at Natural Bridge
Road
- Union at Natural Bridge Road
- I-70
- Riverview
- Jennings Station
- Northland
- Chambers Road at W. Florissant
Ave.
- Florissant Valley Community College
It would be completed in two phases
with the first phase ending at the
Northland Shopping Center in Jennings.
The cost for the entire route would
be $485.5 million.
The East-West Gateway directors also
included a link between the north expansion
and the west expansion that would follow
the Terminal Railroad right-of-way
connection designed to help people
in north St. Louis to get to jobs in
West County. There is no cost estimate
as of yet for this link.
Alternative 3 Light Rail Transit
Alternative 3 follows:
- 14th Street
- Chouteau Ave.
- Union Pacific Railroad Right-of-Way
- At Loughborough, I-55 Right-of-Way
- At Bayless, Trailnet Grant's Trail
- Cross County MetroLink Segment
II
This route would connect in Green Park
with the Cross County Phase II extension
from Shrewsbury to Interstate 55 and
Butler Hill Road in Oakville.
Planners designated the following
stations for this alternative:
- Kiel Center Station on the existing
- MetroLink alignment
- 14th Street at Chouteau
- Jefferson at Chouteau
- Grand Ave. at Chouteau
- Shaw at I-44
- Arsenal
- Chippewa near Gravois
- Itaska at Delor
- Loughborough at I-55
- Bayless at I-55
- Reavis Barracks at I-55
- Green Park
- South County Center
- Butler Hill at I-55
The cost for this route would be $614.3
million.
Alternative 3Light Rail Transit
Alternative 3 follows:
- Rock Island Right-of-way and Page
- Avenue to the WestPort Plaza area.
Planners designated the following
stations for this alternative:
- Dielman at the Rock Island Right-of-way
- Lindbergh at the Rock Island Right-of-way
- Westport
The cost would be $249.5 million.